System Improvement Project Updates

Welcome to our System Improvement Project Updates page. Here, you will find information regarding our ongoing and upcoming projects.

This section is dedicated in loving and grateful memory of Warren Musselman, whose passion and service deeply impacted our community. We are proud to continue the work they cared so much about.

Thank you for your continued patience and support as we work to maintain and improve our district.

6-27-2026: Construction Update 

Button Rock Road – CCI crews have completed work along the entire length of Button Rock Road and are now in the final stages of cleanup and site restoration.

Wichita Street – The new main water line installation is complete. Work is now shifting to connecting individual service lines to the new main.

Cree Street – The new main water line has been installed and is currently undergoing pressure testing and quality assessments. As with Wichita Street, service line connections are the next phase of work.

Service Line Connections (Cree & Wichita Streets) – Service lines for both streets still need to be installed. This work will require new trenching from the main line to the meter pit at each home, followed by testing. Residents should expect this phase to take some additional time to complete.

Hopie Street / Kiowa Street – A temporary water line is currently in place between Hopie and Kiowa Streets while work continues in the area.

As always, please use caution when driving through the District. Road crews and construction equipment are active throughout the work zones — slow down and remain alert.

We want to extend our sincere appreciation to the CCI crew members and support staff for their hard work and the quality results they continue to deliver on these projects.

Please note that this update reflects our best available information at the time of publication and is subject to change as conditions on the ground evolve.