Nov 21, 2025  Construction Update: Per today's Construction Project Meeting we know that all materials are onsite to complete the water main install and the crew is currently working on it.
Remaining work is to finish:
- Installing valves, flushing hydrants and anchor blocks
- Installation of a new zone meter pit by the Cherry Company
- Pressure testing and disinfection of the new lines
- Connection of individual service lines back to their meters
- Removal of the temp lines
- Restoration of the road and other disturbed ground.
- Re-vegetation will occur in the Spring.
They're already well along on the first item and plan on working Saturdays and bringing on a 2nd crew so that multiple tasks can be completed at the same time. There will be some road closures during this period but traffic plates will be installed over any open excavations outside working hours.
Provided we have no significant weather delays, the contractor feels confident that all work on the Buttonrock section of the project will be completed by December 9th, 2025

Nov 17, 2025 Regular Meeting Date Change: the water board will be hosting its monthly meeting this Wednesday, November 19th at 7pm in order to avoid schedule conflicts with the upcoming holiday. You can join the meeting on Zoom by clicking HERE.

Nov 14, 2025 Special Meeting Notice: the water board will be conducting a special meeting in person at the fire station (with Zoom access available) this Sunday, Nov 16th at 7pm local time. The purpose is to discuss HR issues. Join the Zoom feed by clicking HERE. Code is 618459.

Nov 11, 2025: Water Outage on West Side: Work continues backfilling the trench where the team replaced 150 feet of water main. They were out until 1AM this morning working on it. 

Unfortunately, it appears not to have solved the water pressure problem completely. While it did resolve some leaks, the problem remains. Cam is out looking for pressure drop locations and the Wolf team and Jen are completing the water main replacement. We are currently looking for other leaks, bad valves and potential blockages. Unfortunately, I can't give you anything further at this time.

Nov 8, 2025 Water Outage on West Side: We're aware of the ongoing water outage on the "dark side" and are working to resolve the issue as soon as possible. 

 

October Meeting Change Notice

MeetingChangeNoticeOct2025.doc

September 25, 2025: 

Some good news from last night's board meeting:

-The bottled water order due to excess Manganese has been lifted.

-Homes that use less than 2,000 gallons in September will not be charged any additional fees for water hauling. Thank you for your continued efforts!

-The new "green sand" filter system for the treatment plant should be arriving next week, and we expect it to go online soon afterward.

-Recent rains have coincided with the return of our water rights "priority", allowing us to draw water from the creek again. Conservation is still VERY important, but this will help to ease our ongoing shortage.

-Our website is under new management, and be updated over the next few weeks to contain more info (including updates like this one) and be easier to navigate.

Agenda&ZoomSeptje.pdfHaulChrgLetJE.pdf

We're working to improve both the timeliness and the organization of the notices on this page. 

 

September 19, 2025 : The boil order issued by CDPHE has been officially rescinded. Please note that the warning about excess Manganese is still in effect at this time. Levels have been dropping after the influx of hauled water, and we hope to have this issue resolved soon as well. 

 

Board Let 9.1.25

TO ALL MEMBERS OF THE PINEWOOD SPRINGS WATER DISTRICT
The water emergency continues, with a general outage affecting everyone on the West side of Route 36.
The cause is that, although we are hauling water as rapidly as possible, we have been unable to keep up
with usage. As a result, water levels in the storage tanks on that side have dropped so low that there is
insufficient hydraulic head to maintain pressure. We presently expect the water outage will last all day today.
We delayed using reservoir water as long as possible due to the high manganese levels. Yesterday, we
started tapping the reservoir as an emergency measure, first flushing the line and diluting the water to
reduce the manganese concentration. It is still higher than the recommended level for health: 0.3 mg/L for
infants under 6 months and 0.5 mg/L for adults.
A complicating factor is that manganese reacts with chlorine, pulling down our disinfectant levels. We must
then add more chlorine to make up the shortage. We are standing by the pumps, restarting and adding
chlorine as needed.
These factors have prompted two health advisories: one to use bottled water for infants and formula, and
one to boil water for drinking due to loss of pressure in the lines.
With the help of the Fire Department, we are distributing these advisories to all members of the community.
Bottled water is available at the Fire House for anyone who needs it, and we will have more at the water
plant. Just let us know.
As soon as we can get the water levels in the tanks high enough, we will restart water to the affected area.
The health advisories will remain in effect until we can get the manganese levels down in our finished water.
We are doing everything to expedite installation of our Pilot Treatment Plant to address the manganese
problem directly.
We are receiving water from several haulers. We expect that the cost of hauled water will average out to at
least $0.20 per gallon.
Please, please do everything you can to CONSERVE WATER. We are working as hard as we can to get it
flowing again, and need your help.
Jim Easter
Kim Bologna
Evan Jones
Patty Peritz

BoardLetter825.pdfColorado Civil Infrastructure.docxCOMMUNITY UPDATEpp7.30.25.pdf

Special Meeting

Discussion on CCI rock removal letter.

June25RockRemovalMeeting.pdf

Topic: Pinewood Springs Water District Special Meeting
Time: May 8, 2025 07:00 PM Mountain Time (US and Canada)
Join Zoom Meeting
https://us02web.zoom.us/j/84029766354?pwd=qRvfOLsGk4xrODPaY4BlhWWkgw8nqi.1
Meeting ID: 840 2976 6354
Passcode: PSWDSpcl
One tap mobile
+17193594580,,84029766354#,,,,*85254336# US
+12532158782,,84029766354#,,,,*85254336# US (Tacoma)

Purpose of May 8th meeting is for the Board to approve a change of the total amount of the reimbursement package to be submitted.  The change is necessary due to the inclusion of an unpaid invoice in the original package that was approved at our Board meeting on April 23. 

PSWD special meeting 050825.pdf

 

Pinewood Springs Water District - Special Financial Meeting
Time: April 2, 2025 07:00 PM Mountain Time (US and Canada)
Join Zoom Meeting
https://us02web.zoom.us/j/83967906167?pwd=MibDomeccQza0KLTRVnauFaOblYVbf.1

 

PSWD Financial Workshop Special Meeting_04.02.25_ 033125_ADA compliant (3).pdf

Pinewood Springs Water District - Special Preconstruction Meeting
Time: April 3, 2025 07:00 PM Mountain Time (US and Canada)
Join Zoom Meeting

agendaPSWD SRF Project Pre-Construction Special Meeting_04.03.25_ 033125_ADA compliant (2).pdf

https://us02web.zoom.us/j/88187914260?pwd=eR9KqiQ8M41gOOROUtlhrKLw2Qa6DX.1

Board Member Election Results

CancellationWaterGB.pdfPNDrinkingWaterCorrectedManganese225.pdfAcute Rescind Bottle Water Advisory.pdfNOTICE OF SPECIAL MEETING_and Agenda_Loan acceptance_02.10.25.docxApprovedPublicNotice13125.pdfPublic notice 01_2025-rev1.pdf

Posted Notices

PSWD_Notice_of_Vacancy_ADA_Compliant_060225.pdfJan25 Special Hearing public noticeV2published.pdfCombineMeetingChangesBudget25Dec24gb.pdfMeetingChangeRateHearingDec24.pdf

Violation Letters

Maximum Contaminate Violation TTHM's & HAA5

PN4thQTRDec24TTHMsgb.pdfPN4thQTRDec24HAA5sPNgb.pdfPN3rdQtr9.3-10.7MWCCgb(3).pdfPN2ndQtrMay24.pdfPN1stQtApril24.pdfPN1stQtrBackflowDevices23.pdf

 

 

Loan & Grant Notices

Public Hearing concerning Loan Application

April24SRFSpecialHearing.pdf

Zoom Recording Public Hearing December 14, 2023

PWSWD-Board-Meeting-20231214(2).mp4

Loan Application and Attachments November 2023

SRF Infra Project_Drinking Water Project Needs Assessment (PNA) Form_Read Only_11-1-2023(4)pp.pdfPSWD_PNA_attachments_10-31-2023pp.pdf

Public Hearing concerning Loan Application

SRF project community email notice for Dec 14th public hearingGB.pdf

December 14, 2023 SRF Public Hearing Zoom Meeting Invite

https://us02web.zoom.us/j/87042610392?pwd=LzdlWEFHS2sxUVdnY2FmUGovbVFLUT09

SPECIAL PUBLIC HEARING

PSWDPublicMeetingNotice_SRF Infra Project_11-10-23_PP.pdf

Special Meeting Work Session

WorkSessionNovember.pdf

PUBLIC HEARING NOTICE

Budget Review and Rules and Regs possible Change with regard to rates Public Hearing.  Also a PUBLIC HEARING to discuss the SRF Project documents has been scheduled for December 14th.

CombineMeetingChangesBudget23PublicHearingV3gb.pdf

 

 

Navajo property Fire Mitigation Project.

FireMitigationNavajoTanks.pdf
https://youtu.be/uoZb7fiaKpk?si=w7qAmHsYv3MfkEoC